Concho Highway Phase 1
| Project
Description |
0.6 mile widening with curb, sidewalk and street
lighting. |
| Start
Date |
June, 2002 |
| Estimated
End Date |
January, 2003 |
| Disruptions |
Traffic limited to one controlled lane
during certain phases, expect minor delays. |
Miscellaneous Chipseal
| Project
Description |
Chipseal of collector and arterial roads. |
| Start
Date |
Ongoing |
| Estimated
End Date |
Ongoing |
| Disruptions |
Traffic limited to one controlled lane
during certain phases, expect minor delays. |
Completion of Frontier Parkway
| Project
Description |
Landscaping, street lights. |
| Start
Date |
May, 2002 |
| Estimated
End Date |
August, 2002 |
| Disruptions |
Intermittent, minor delays |
Completion of Wastewater Treatment Plant
| Project
Description |
Doubling of current plant capacity. |
| Start
Date |
2001 |
| Estimated
End Date |
June, 2002 |
| Disruptions |
No
disruption of service planned. |
Upgrades to Sewer Lift Stations
| Project
Description |
9 lift stations improvements with remote
monitoring and battery backup. |
| Start
Date |
January, 2002 |
| Estimated
End Date |
January, 2003 |
| Disruptions |
Residents might experience slow drainage, or might be notified and
asked to reduce usage. |
Town of Snowflake
Department of Public Works
81 West 1st South
Snowflake, Arizona 85937
(928) 536-7103, ext. 255
(928) 536-2539 FAX
public_works@ci.snowflake.az.us
|
|